A contractor may claim an amount, but the project must still verify what has actually been completed, accepted and contractually payable.
Managing construction, renovation, or fit-out projects in Thailand involves careful oversight of payments to contractors. Foreign property owners, developers, investors, and hospitality operators often face challenges ensuring that payments reflect the true progress of work. This article explains why a contractor’s progress claim should be assessed against verified work, contractual requirements, and supporting evidence before payment is certified.
Understanding Progress Claims, Payment Certificates, and Actual Payments
A contractor’s progress claim is a request for payment based on work they say has been completed. However, submitting a claim does not automatically mean the amount is payable. There are several distinct steps in the payment process:
Contractor Progress Claim: The contractor submits a statement of work done and materials supplied, requesting payment.
Independent Review: A qualified party inspects and verifies the claimed work and materials.
Payment Recommendation or Certificate: Based on the review, a payment certificate is issued recommending the amount to be paid.
Actual Payment: The client or project owner makes payment according to the certificate.
It is essential to understand that the claim is only a starting point. The project team must verify the claim against contractual terms and evidence before certifying payment. Paying based on assumptions or unverified claims risks overpayment, disputes, and project delays.
The Contractual Basis for Progress Claims
Progress claims must align with the contract’s payment framework. Key contractual elements include:
Contract Price and Bill of Quantities (BoQ): The agreed total price and detailed quantities of work items.
Work Packages and Payment Milestones: Defined stages or packages of work triggering payments.
Approved Variations: Changes to the original scope that have been formally approved.
Retention: A percentage of payment withheld to ensure satisfactory completion.
Taxes and Advance-Payment Recovery: Tax obligations and deductions for any advance payments made.
Materials-on-Site Rules: Conditions under which payment for materials stored on site is allowed.
Supporting Documents: Invoices, delivery notes, inspection reports, and other evidence required by the contract.
Understanding these elements helps ensure that progress claims are assessed fairly and accurately.
Reviewing Completed Work with Verified Evidence
Verification of completed work involves more than trusting the contractor’s statement. The review should include:
Verified Quantities: Measurements confirmed by site inspectors or quantity surveyors.
Site Inspection: Physical checks to confirm work quality and completeness.
Approved Drawings and Specifications: Comparing work against the latest approved plans.
Inspection Records and Photographs: Documentation of work progress and quality.
Test Results: Evidence that materials and workmanship meet required standards.
Accepted Work Areas: Confirmation that the client or consultant has accepted the work.
Programme Status: Progress relative to the project schedule.
Previous Certified Amounts: Ensuring no double payment for earlier work.
This thorough review protects the client from paying for incomplete or defective work.

Eye-level view of construction site showing verified progress and inspection activities.
Checking Materials Claimed on Site
Claims for materials stored on site require careful scrutiny. The review should confirm:
Purchase Orders or Invoices: Proof of purchase matching claimed quantities.
Delivery Records: Evidence that materials arrived on site.
Quantity and Condition: Materials are in the correct amount and undamaged.
Approved Specification: Materials meet contract requirements.
Secure Storage: Materials are stored safely to prevent loss or damage.
Ownership or Payment Terms: Clarify if payment for materials on site is allowed and under what conditions.
Insurance Coverage: Materials are insured if required by contract.
Not all contracts allow payment for materials on site before installation. Confirming these details prevents premature or unsupported payments.
Handling Variations Separately and Carefully
Variations are changes to the original contract scope. Only variations that are:
Properly Instructed: Formal instructions issued by the client or consultant.
Priced: Valued according to agreed rates or negotiated prices.
Approved: Accepted through the project’s change-control process.
should be included in progress claims. Informal discussions or contractor proposals do not constitute approved variations. Including unapproved variations in payment claims can lead to disputes and financial risk.
Adjusting Payments for Incomplete or Defective Work
Payment assessments must deduct or adjust amounts for:
Incomplete Work: Work not finished as per contract requirements.
Defective or Rejected Work: Work failing quality standards or rejected by the client.
Missing Evidence: Lack of supporting documents or verification.
Unapproved Variations: Work not formally approved.
Previous Payments: Avoid double payments for the same work.
Advance Recovery and Retention: Contractual deductions for advances and retention sums.
Unsupported Materials Claims: Materials without proper proof or approval.
These adjustments ensure payments reflect actual, acceptable progress.

High angle view of securely stored construction materials awaiting installation.
Recording the Assessment Clearly and Transparently
A clear record of the payment assessment should include:
Amount claimed by the contractor.
Amount verified through inspection and measurement.
Amount adjusted and reasons for adjustment.
Amount previously certified.
Current recommended payment amount.
Cumulative certified amount to date.
Unresolved items or disputes.
Name of the reviewer and date of assessment.
This documentation supports transparency and helps resolve any future disagreements.
Supporting Progress Percentages with Measurable Evidence
Progress percentages should be based on measurable evidence such as:
Verified quantities completed.
Accepted work areas.
Inspection and test results.
Programme milestones achieved.
Invoices or expenditure alone do not prove physical progress or acceptance. Relying solely on financial data risks paying for work not yet done or accepted.
Maintaining a Comprehensive Evidence File
An evidence file should be maintained for each progress claim, containing:
The contractor’s claim document.
Valuation sheets and measurement records.
Inspection reports and photographs.
Delivery and purchase documents for materials.
Approved variation orders.
Test and quality assurance records.
Payment certificates and approval records.
Correspondence related to the claim.
This file supports the payment decision and provides a clear audit trail.

Close-up view of inspection records and photographs used to verify construction progress.
Common Mistakes to Avoid in Progress Claim Payments
Avoid these frequent errors:
Paying the claimed amount without verification.
Using unsupported percentage completion figures.
Paying for delivered but unaccepted materials.
Including unapproved variations in payments.
Failing to deduct previous payments or advances.
Ignoring defective or rejected work.
Mixing owner-purchased materials with contractor claims.
Certifying work without photographs or measurements.
Failing to explain adjustments clearly.
Treating payment as final acceptance of quality.
Avoiding these mistakes protects project budgets and quality.
Final Thoughts on Progress Claims and Payment Certification
A disciplined payment review should create a clear record of what was claimed, what was verified, what was adjusted and why. This approach ensures payments reflect actual, accepted work and contractual terms.
At AD ASIA Consulting, we support clients with services including progress verification, quantity review, payment assessment, variation tracking, cost reporting, and construction management. Our expertise helps foreign investors and developers in Thailand manage payments confidently and avoid costly errors.
If you are managing a construction project in Thailand, consider requesting a Progress Claim and Payment Review to ensure your payments are accurate and justified.
Disclaimer: Valuation, certification, retention, tax, variation, and payment requirements must be assessed under the specific project contracts by qualified professionals. This article provides general guidance and does not replace professional advice.
This article was prepared by AD ASIA Consulting to assist foreign property owners, developers, investors, and hospitality operators managing construction projects in Thailand.




Comments