Requests for Information: How Unresolved Design Questions Affect Cost and Time
An unanswered site question rarely remains isolated. It can affect labour, materials, inspections, variations and the completion programme.
Managing construction, renovation, or fit-out projects in Thailand involves many moving parts. When design questions arise on site, leaving them unresolved can cause delays and increase costs. A controlled Request for Information (RFI) process helps clarify missing, conflicting, or unclear project details before they disrupt progress. This article explains how RFIs work, what they should include, common pitfalls, and why managing them properly benefits your project.
What Is an RFI and Why Is It Important?
An RFI is a formal request for clarification sent during construction when drawings, specifications, site conditions, or instructions are missing, unclear, or inconsistent. It acts as a communication tool between contractors, designers, and clients to resolve uncertainties before work continues.
For example, if a drawing shows two different wall thicknesses for the same location, or if dimensions are missing, an RFI is raised to ask for clarification. Without this, workers might guess or proceed incorrectly, leading to rework or delays.
Common reasons for RFIs include:
Conflicting drawings or specifications
Missing dimensions or details
Structural and mechanical, electrical, plumbing (MEP) clashes
Unclear materials or finishes
Unknown existing site conditions
Undefined responsibility for certain tasks
By addressing these issues early, RFIs help keep the project on track.
What Should Each RFI Contain?
A well-prepared RFI includes specific information to ensure clear communication and timely resolution. Each RFI should have:
Unique reference number for tracking
Date of submission
Affected location on site (e.g., floor, room number)
Drawing or specification reference related to the question
Clear and concise question explaining what needs clarification
Reason for clarification to explain why the question matters
Affected activity (e.g., installation, inspection)
Responsible reviewer who will answer the RFI
Required response date to keep the schedule on track
Supporting documents such as photographs or marked-up drawings
Possible cost or programme impact if known
Including these details helps reviewers understand the issue quickly and provide accurate answers.
Why Vague Questions Cause Problems
Questions like “Please clarify urgently” or “What should we do here?” are difficult to answer. They lack context and specifics, forcing reviewers to guess what the problem is. This slows down responses and increases the chance of misunderstandings.
Clear, focused questions save time. For example, instead of “Please clarify the wall,” ask “The wall thickness on drawing A-101 differs between 150mm and 200mm. Which is correct for the lobby wall at gridline B3?”

Using an RFI Register to Track Progress
An RFI register is a simple but essential tool to manage all RFIs in one place. It records:
The question raised
Originator (who asked)
Reviewer (who answers)
Deadline for response
Current status (open, answered, closed)
Final answer provided
Affected work package or trade
Follow-up actions required
This register helps project managers monitor outstanding RFIs, avoid overdue responses, and ensure all issues are resolved before work proceeds.
When an RFI Response Changes the Project Scope
Sometimes, an RFI response clarifies the existing design without changes. Other times, it reveals that scope, materials, quantities, cost, or programme must be adjusted. In such cases, the response may require:
Revised drawings or specifications
Formal instructions from the client or consultant
A variation process to approve changes and costs
Proper documentation ensures that changes are tracked and agreed upon, avoiding disputes later.
How Unanswered RFIs Affect Construction
Leaving RFIs unanswered or unresolved can disrupt many aspects of construction:
Labour sequencing: Workers may wait or proceed incorrectly, causing delays or rework
Procurement: Materials may be ordered late or wrong items supplied
Inspections: Delays in approvals or missed inspections for concealed work
Subcontractors: Confusion over responsibilities or scope
Testing and commissioning: Incomplete or incorrect installations affect final testing
Completion programme: Overall project timeline extends, increasing costs

Cost Impacts of Poor RFI Management
Unresolved RFIs can lead to several cost issues:
Idle labour waiting for instructions
Remobilisation costs when work stops and restarts
Rework due to incorrect installations
Wasted materials from wrong orders or damage
Expedited procurement fees to meet delayed schedules
Extended site overheads such as equipment rental and supervision
These costs add up quickly and reduce project profitability.
Proper Closure of RFIs
Closing an RFI properly means:
Confirming the response fully answers the question
Issuing revised documents if needed
Informing all affected parties (contractors, suppliers, inspectors)
Updating procurement and programme records
Assessing cost and time impacts
Verifying implementation on site
Skipping these steps risks recurring issues and confusion.
Common Mistakes to Avoid
Some frequent errors in RFI management include:
Vague or incomplete questions
Missing drawing or specification references
Sending RFIs to the wrong reviewer
Verbal answers without written records
Overdue or ignored responses
Changing scope informally through RFI answers
Closing RFIs before changes are implemented
Failing to update drawings and registers after resolution
Avoiding these mistakes improves communication and project control.

How AD ASIA Consulting Supports Effective RFI Management
At AD ASIA Consulting, we understand the challenges foreign property owners, developers, investors, and hospitality operators face in Thailand’s construction environment. Our services include:
RFI management to ensure all design questions are tracked and resolved efficiently
Design coordination to identify and resolve clashes before construction starts
Programme review to keep your project on schedule despite changes
Change control to manage variations and cost impacts formally
Construction management to oversee site activities and ensure quality
These services help prevent unresolved information from silently disrupting the construction sequence. We invite you to request an RFI and Design Coordination Review to safeguard your project’s success.
The purpose of an RFI is not to create more paperwork. It is to prevent unresolved information from silently disrupting the construction sequence.