Requests for Information: How Unresolved Design Questions Affect Cost and Time

3 minutes ago
4 min read

An unanswered site question rarely remains isolated. It can affect labour, materials, inspections, variations and the completion programme.


Managing construction, renovation, or fit-out projects in Thailand involves many moving parts. When design questions arise on site, leaving them unresolved can cause delays and increase costs. A controlled Request for Information (RFI) process helps clarify missing, conflicting, or unclear project details before they disrupt progress. This article explains how RFIs work, what they should include, common pitfalls, and why managing them properly benefits your project.



What Is an RFI and Why Is It Important?


An RFI is a formal request for clarification sent during construction when drawings, specifications, site conditions, or instructions are missing, unclear, or inconsistent. It acts as a communication tool between contractors, designers, and clients to resolve uncertainties before work continues.


For example, if a drawing shows two different wall thicknesses for the same location, or if dimensions are missing, an RFI is raised to ask for clarification. Without this, workers might guess or proceed incorrectly, leading to rework or delays.


Common reasons for RFIs include:


  • Conflicting drawings or specifications

  • Missing dimensions or details

  • Structural and mechanical, electrical, plumbing (MEP) clashes

  • Unclear materials or finishes

  • Unknown existing site conditions

  • Undefined responsibility for certain tasks


By addressing these issues early, RFIs help keep the project on track.



What Should Each RFI Contain?


A well-prepared RFI includes specific information to ensure clear communication and timely resolution. Each RFI should have:


  • Unique reference number for tracking

  • Date of submission

  • Affected location on site (e.g., floor, room number)

  • Drawing or specification reference related to the question

  • Clear and concise question explaining what needs clarification

  • Reason for clarification to explain why the question matters

  • Affected activity (e.g., installation, inspection)

  • Responsible reviewer who will answer the RFI

  • Required response date to keep the schedule on track

  • Supporting documents such as photographs or marked-up drawings

  • Possible cost or programme impact if known


Including these details helps reviewers understand the issue quickly and provide accurate answers.



Why Vague Questions Cause Problems


Questions like “Please clarify urgently” or “What should we do here?” are difficult to answer. They lack context and specifics, forcing reviewers to guess what the problem is. This slows down responses and increases the chance of misunderstandings.


Clear, focused questions save time. For example, instead of “Please clarify the wall,” ask “The wall thickness on drawing A-101 differs between 150mm and 200mm. Which is correct for the lobby wall at gridline B3?”



Eye-level view of construction site with workers reviewing drawings
Eye-level view of construction site with workers reviewing drawings


Using an RFI Register to Track Progress


An RFI register is a simple but essential tool to manage all RFIs in one place. It records:


  • The question raised

  • Originator (who asked)

  • Reviewer (who answers)

  • Deadline for response

  • Current status (open, answered, closed)

  • Final answer provided

  • Affected work package or trade

  • Follow-up actions required


This register helps project managers monitor outstanding RFIs, avoid overdue responses, and ensure all issues are resolved before work proceeds.



When an RFI Response Changes the Project Scope


Sometimes, an RFI response clarifies the existing design without changes. Other times, it reveals that scope, materials, quantities, cost, or programme must be adjusted. In such cases, the response may require:


  • Revised drawings or specifications

  • Formal instructions from the client or consultant

  • A variation process to approve changes and costs


Proper documentation ensures that changes are tracked and agreed upon, avoiding disputes later.



How Unanswered RFIs Affect Construction


Leaving RFIs unanswered or unresolved can disrupt many aspects of construction:


  • Labour sequencing: Workers may wait or proceed incorrectly, causing delays or rework

  • Procurement: Materials may be ordered late or wrong items supplied

  • Inspections: Delays in approvals or missed inspections for concealed work

  • Subcontractors: Confusion over responsibilities or scope

  • Testing and commissioning: Incomplete or incorrect installations affect final testing

  • Completion programme: Overall project timeline extends, increasing costs



High angle view of construction materials piled on site awaiting installation
High angle view of construction materials piled on site awaiting installation


Cost Impacts of Poor RFI Management


Unresolved RFIs can lead to several cost issues:


  • Idle labour waiting for instructions

  • Remobilisation costs when work stops and restarts

  • Rework due to incorrect installations

  • Wasted materials from wrong orders or damage

  • Expedited procurement fees to meet delayed schedules

  • Extended site overheads such as equipment rental and supervision


These costs add up quickly and reduce project profitability.



Proper Closure of RFIs


Closing an RFI properly means:


  • Confirming the response fully answers the question

  • Issuing revised documents if needed

  • Informing all affected parties (contractors, suppliers, inspectors)

  • Updating procurement and programme records

  • Assessing cost and time impacts

  • Verifying implementation on site


Skipping these steps risks recurring issues and confusion.



Common Mistakes to Avoid


Some frequent errors in RFI management include:


  • Vague or incomplete questions

  • Missing drawing or specification references

  • Sending RFIs to the wrong reviewer

  • Verbal answers without written records

  • Overdue or ignored responses

  • Changing scope informally through RFI answers

  • Closing RFIs before changes are implemented

  • Failing to update drawings and registers after resolution


Avoiding these mistakes improves communication and project control.



Eye-level view of project manager reviewing RFI register on laptop
Eye-level view of project manager reviewing RFI register on laptop


How AD ASIA Consulting Supports Effective RFI Management


At AD ASIA Consulting, we understand the challenges foreign property owners, developers, investors, and hospitality operators face in Thailand’s construction environment. Our services include:


  • RFI management to ensure all design questions are tracked and resolved efficiently

  • Design coordination to identify and resolve clashes before construction starts

  • Programme review to keep your project on schedule despite changes

  • Change control to manage variations and cost impacts formally

  • Construction management to oversee site activities and ensure quality


These services help prevent unresolved information from silently disrupting the construction sequence. We invite you to request an RFI and Design Coordination Review to safeguard your project’s success.



The purpose of an RFI is not to create more paperwork. It is to prevent unresolved information from silently disrupting the construction sequence.



Disclaimer: Design responsibility, instructions, variations, and entitlement to time or cost require project-specific professional and contractual review.